Project Information

The Tuam St project involved the replacement of an old brick barrel pipeline with a new DN1200 plastilined concrete pipe along with associated manholes and service relocation.

 

Project Description

The scope included sewer diversion of the normal flows through the old brick barrel, breaking out of the existing sewer, construction of the new pipeline, construction of new manholes, watermain relocation and local sewer relocation.

 

Owner:
Christchurch City Council 

 

Engineer:
CCC

 

Period of works:
2019-2021

 

Technique implemented:
Sheetpile open trenching, concrete construction

 

Value:
$12m

 

0m
Length
0DN
Pipe Diameter
0m
Ave Depth